Recent orders:
Deza

New reinforced-concrete chimney height 70 meters - DEZA, a.s

reinforced-concrete chimney height 70 m, inner diameter of the stuck 2,60m, protective ceramic liner

Chotíkov

New steel chimney height 80 meters Chotíkov ZEVO Chotíkov

steel chimney height 80 m, the outer diameter of stuck 2900 mm, protective ceramic liner, the chimney is sheathed for completion of overall architectural design appearance incinerator

Velvary

Lining of the rotary furnaces Delta for melting scrap aluminum 12t, MTC, a.s. Velvar

demolition of original damaged brickwork, installation of anchors, new refractory lining


 
  • All work undertaken in fulfilling the task"Repair of head of reinforced concrete chimney 300 m" in Chvaletice power station were by supplier ARCO F.P.S. Pexidr s.r.o. properly and professionally executed without complaints. Contractual terms were complied with. –Luboš Kučera, Sev.en EC, a.s.

  • Supplier ARCO F.P.S. Pexidr s.r.o. ensured for our company contract "Modernization of the cooling circuit for the heating plant Komořany - Modernization of cooling tower no. 2." Object of the contract was also sanitation of cooling tower no 2. The cooling tower is permanently exposed to influence of aggressive water and weather conditions. All work undertaken in fulfilling the above-mentioned orders by supplier ARCO F.P.S. Pexidr were carried out properly and professionally. –Ing. Jan Sulík, United Energy, a.s.

  • The company ARCO F.P.S. Pexidr s.r.o. provided for our company work "Removing of the audit findings on the chimney VGH / 12H101 in the company premises Slovnaft a.s.". All work carried out within the framework of fulfillment of the above works have been by supplier ARCO F.P.S. Pexidr s.r.o. properly and professionally performed without complaint. the agreed terms have been complied with. –Ing. Martin Lidák, SLOVNAFT MONTÁŽE A OPRAVY a.s.